The project is however 2.85% behind the 50.4% scheduled progress.
State Public Works, Utilities and Transportation Committee chairman Lim Hock Seng said concession holder Jambatan Kedua Sdn Bhd (JKSB) had assured the state government that it would catch up with the scheduled completion of the 24km bridge slated for November 2013.
Construction works on the bridge started in late November 2008.
Lim also said over 700 workers were working round the clock at the United Engineers Malaysia (UEM) segmental box girder plant in Batu Kawan to produce 8,092 units of segmental box girders for the bridge.
“They have already moulded 987 units. A total of 28 units are already fixed on-site out in the sea with 14 of them on each side of the bridge.
“Besides that, piling works are 84% completed while the building of pile caps and columns are 55% and 45% completed respectively,” he said during a visit to the plant yesterday.
Lim added that the two toll plaza buildings, to be located in Batu Kawan, were still on the design board.
“We will also implement a green concept for the package to be environmental friendly,” he added.
Buildcast Sdn Bhd (a wholly-owned subsidiary of UEM Builders Bhd) production manager Anuar Abdul said there were 22 moulds and three factories at the segment casting plant.
“Between 12 and 14 pieces of segmental box girders are produced in a day and the process is a tedious one,” he said.
The RM4.5bil second bridge project comprises three main packages — construction of the sub-structure by CHEC Construction Sdn Bhd (the local arm of China Harbour Engineering Co Ltd), casting of the segmental box girder by UEM Builders Bhd, and construction of the Batu Kawan and Batu Maung exit and entry points and trumpet interchange by Cergas Murni, IJM Construction and HRA Teguh.
The bridge, which will link Batu Kawan in Seberang Prai to Batu Maung on Penang island, is poised to be the longest bridge in the country and Southeast Asia.
By The Star